Hindustan Steel Works Construction Ltd., Appellant; V. Tarapore & Co. And Another, Respondents., 1996-(005)-SCC -0034 –SC
Difficulties to enforce claims for damages:
Para 9: The courts are not concerned with their difficulties to enforce such claims; these are risks which the merchants take. In this case the plaintiffs took the risk of the unconditional wording of the guarantees. The machinery and commitments of banks are on a different level.
Pendency of Arbitration Proceeding – No ground for Injunction:
Para 23: ….. The special circumstances and/or special equities which have been pleaded in this case are that there is a serious dispute on the question as to who has committed breach of the contract, that the contractor has a counter-claim against the appellant, that the disputes between the parties have been referred to the arbitrators and that no amount can be said to be due and payable by the contractor to the appellant till the arbitrators declare their award. In our opinion, these factors are not sufficient to make this case an exceptional case justifying interference by restraining the appellant from enforcing the bank guarantees. The High Court was, therefore, not right in restraining the appellant from enforcing the bank guarantees.
Home | Contact Designed and Maintained by DELHIADVOCATE. © 1999 - 2010 DELHIADVOCATE Last Updated: 15 July 2010 |