Ansal Engineering Projects Ltd., Petitioner; V. Tehri Hydro Development Corporation Ltd., And Another, Respondents. 1996-(005)-SCC -0450 –SC
Pendency of Proceeding for damages – No ground for Injunction:
Para 5: It is equally settled law that in terms of the bank guarantee the beneficiary is entitled to invoke the bank guarantee and seek encashment of the amount specified in the bank guarantee. It does not depend upon the result of the decision in the dispute between the parties, in case of the breach. …….. This reasoning would clearly indicate that the final adjudication is not a precondition to invoke the bank guarantee and that is not a ground to issue injunction restraining the beneficiary to enforce the bank guarantee.
(Para 23 of the case of Hindustan Steelworks Construction Ltd. v. Tarapore & Co. [(1996) 5 SCC 34 : JT (1996) 6 SC 295] was cited with approvable.)